 |
TF2000 Stair Fire Test Summary Report
|
| © Chiltern
International Fire |
| Commercial in Confidence |
| Report reference: TF2000 - Stair Fire Test |
Prepared by:
- Mostyn Bullock, Principal Engineer, Chiltern International
Fire/TRADA Technology Ltd, UK
- Tom Lennon, Senior Engineer, Building Research Establishment
(BRE), UK
- Vahik Enjily, Programme Manager Timber Engineering,
Building Research Establishment (BRE), UK
|
A Single Timber Stair for a Six Storey Timber
Building?
Introduction
Figure 1 shows the TF2000 building at BRE, Cardington.
This building is the largest of its type in the world and is
a timber frame residential building comprising of 4 flats in
each of the six storeys. The height of the top storey (5th floor – level
6) above ground floor level in the building is approximately
13m. The TF2000 building is fitted with a single stair of timber
construction that is located in a stair shaft the walls of which
are of timber frame construction. In the photograph the stair
shaft is seen as the projection from the centre of the front
elevation. Figure 2 is a typical floor plan for the building
showing the location of the stairs in relation to adjacent flats,
storage and common areas.
Figure 2 Typical Floor Plan © Chiltern
Relationship to Current Statutory Guidance
Compliance with current statutory guidance relating
to fire safety in support of the Building Regulations in England
and Wales or Scotland would mean that a building like TF2000
would not be built.
The guidance of the Approved Document B of the
England & Wales Building Regulations recommends that a single
stair serving a building of the height of the TF2000 building
should be constructed from materials of limited combustibility.
Timber does not fall into this material classification (evaluated
by means of the test standard BS476: Part 11) and would necessitate
construction of a stair from materials such as concrete or steel.
For a building of the height of TF2000, compliance
with the Scottish Technical Standards would require the enclosure
of the stair and lobby to be of non-combustible construction.
The stairs, landings and lobby floors would also need to be of
non-combustible construction (as evaluated by means of the test
standard BS476: Part 4). This is independent of whether the building
is served by a single or multiple stairs. This would completely
preclude the use of timber construction in the stair cores of
a building like TF2000 in Scotland.
One of the main advantages of Timber Frame in
the construction market is the speed at which buildings can be
erected and commissioned. If a significant part of the construction
involved the construction or casting of masonry elements then
such benefits would be largely lost at cost to both the developer
and client.
The above issues gave rise to a research proposal,
supported by DETR and the timber construction industry, to carry
out an experimental programme investigating the actual fire performance
of timber stairs in a timber frame building.
The intention was that the results of the stair
tests would provide data that would assist regulators in the
United Kingdom to consider changes leading to a possible harmonisation
of the technical guidance in support of their Building Regulations.
It was necessary to define at an early stage
the fire performance objectives for a stair in such a residential
building during a fire situation. In meeting the fire safety
requirements of the Building Regulations the fundamental consideration
for the stair is as follows:
The
stair has to remain usable for firefighting after initial
evacuation of occupants immediately at risk and for subsequent
evacuation by the other occupants of the flats who are initially
advised to remain in their dwellings.
In the event of a fire in the TF2000 building
the stair will be used by the fire brigade, upon attendance at
the scene, to gain rapid access to the building to remove any
people who are immediately at risk from the fire. Upon completion
of this duty, the stair will provide the access for the fire
brigade to fight the fire from inside the building. Once the
fire has been brought under control or extinguished the stair
would then be used to complete the safe evacuation of other occupants.
During all these operational phases the stair
must remain usable. It must continue to support its design load
for the duration of the incident and must not itself contribute
significantly to a state of fire development that would render
the stairwell space inaccessible to firefighters.
In terms of fire, the most onerous situation
was regarded as one where the fire is actually in the stair itself.
A fire that starts and grows in the stair may arise due to materials
being left or stored in the stairwell that are then either accidentally
or purposefully ignited.
It was recognised that a large fire load in
the stairwell could result in the development of untenable conditions
for means of escape from heat, smoke and toxic fumes. This could
happen at an early stage independent of the type of construction
of the stair enclosure and stairs themselves.
With these points in mind it was proposed that
the stair in the TF2000 building should demonstrate a significant
resistance to becoming involved in a fire when subjected to an
appropriately severe fire source that is in intimate proximity
to exposed timber components of the stair. The resulting fire
(including any contribution from the stair construction) should
not cause the loadbearing capacity of the stair to be reduced
below a serviceable level and should not cause a breach of the
compartmenting elements of structure enclosing the stair.
Stair Specification
It was recognised at an early stage that, in
order to satisfy the identified functional performance requirements
it would be necessary to modify the reaction to fire characteristics
of the timber of the stair. Concerns that were expressed relating
to durability of such protection indicated that the most appropriate
course of action would be to utilise impregnated fire protective
timber treatments rather than those which are surface applied.
It was considered that a scissors stair would
represent the most onerous case in terms of potential fire propagation
and that the results of a test on a scissors stair could be conservatively
applied to single rise stairs.
In order for the results from the project to
have a wide field of application the new stairs were constructed
from Whitewood which, at the time of the project, represented
a commonly imported timber variety used in the construction of
timber stairs. Both the sapwood and heartwood of this type of
timber have a low permeability and therefore are not penetrated
to a significant depth by pressure impregnated timber treatments.
A penetration depth of between 1 and 2mm is normal for this type
of timber. The sapwood of Redwood for instance is very permeable
and can be completely penetrated by impregnation treatments at
significant section sizes. Thus if Whitewood could be shown to
produce an adequate performance then other timber species having
a higher permeability could be assumed to potentially provide
at least an equal performance under the same fire conditions.
In all tests the stairs were underdrawn with
a single layer of 12.5mm thick Gypsum wallboard that was fixed
to the stringers of the stair (without cross noggins) at 150mm
centres.
Trial Tests
The purpose of the trials was to ascertain the
required level of protection to a commonly used timber stair
specification in order to achieve these performance attributes.
For the trials, a purpose built compartment
of similar dimensions and construction to the existing TF2000
stair shaft was built in the Cardington hangar.
In terms of the design fire, the intention was
to simulate a deliberate fire event where a double mattress stored
in the stair shaft at ground floor level had been doused with
an accelerant and ignited. For the purposes of the experiments,
the mattress was set in a steel tray and fixed to the handrail
of the lower flight of stairs. This guaranteed that the mattress
would not slump over and thus ensured that the mattress, once
ignited, burned with maximum intensity. Approximately one litre
of paraffin was poured onto porous fibre strips placed alongside
the mattress in the steel tray.
The double mattresses used were identical for
each test and were purchased from a high street retailer. The
mattresses were labelled as complying with latest fire safety
regulations in force for such products.
The stairs for the first trial were not provided
with a fire retardant treatment. In the trial complete combustion
of the mattress took place. The spindles and handrail of the
baluster were involved in the fire causing extensive charring
to these members. However, virtually no damage was inflicted
on the stair treads and risers, and only very limited charring
to the vertical face of the lower stringer was observed.
An attempt was then made to initiate a trench
effect by placing paraffin soaked fibre strips at the junction
between the treads and risers of the first five steps of the
lower flight. Approximately 0.5 litres of paraffin was used.
Ignition of the strips led to a short period of sustained flaming
where flames were observed ‘lying down’ and surface
charring of 2 to 3 mm on the first five steps was the result.
The fire died out as the strips and paraffin were completely
consumed and there was no further spread of flame. The structural
integrity of the stairs was maintained and verified by personnel
walking on the treads.
The final phase of this first trial involved
removing the plasterboard to the underside of the stair and building
a small crib (16 sticks of 50x50x500mm softwood) underneath the
lower surface of the first flight. Again approximately 0.5 litres
of paraffin was used to initiate burning. This final test led
to a break through of the fire on the stairs and the string after
approximately 10 minutes with the lower flight becoming fully
involved in the development of the fire. The test fire was vented
and extinguished using a fire hose reel to prevent the fire in
the compartment from reaching an imminent flashover.
Figure
3 shows the temperature of the lower flight of stairs,
the air temperature immediately above the mattress and the
oxygen concentration in the compartment over the complete duration
of the trial.
For the second trial timber stair components
were treated using Dricon by Hickson Timber Products Ltd.
After treatment and kiln drying, the components
were returned to Cardington and assembled on site. This second
trial was performed in two stages. The first involved the mattress
and fibre strips placed at the intersection of the treads and
risers of the first flight (see Figure 4).
The second stage consisted of removal of the plasterboard fixed
to the underside of the stairs and ignition of a single crib
immediately below the first flight.
The mattress fire test did not cause any significant
damage to the stair. The treatment clearly provided an enhanced
performance over that observed during Trial 1. The mattress burned
for approximately 13 minutes. The inclusion of the fibre strips
on the treads of the lower flight led to limited charring (approximately
5mm) on the face of the risers in the immediate area around the
fibre board. However, there was no evidence of flaming on the
nosing, string or even on the treads and risers remote from the
fibre strips. In general the spindles on the lower flight remained
intact with only limited localised charring on the handrail closest
to the mattress. Surface charring was observed on the lower string
to a depth of 6 or 7mm with a maximum depth in a very localised
area of 10mm or approximately half the thickness. In general
there was no spread of flame away from the immediate vicinity
of the mattress. There was limited charring (approximately 3mm)
on the upper flight spindles and a similar level on the upper
string.
The second phase consisted of the crib burn
under the first flight, with the plasterboard to the underside
of the stairs removed for both flights.
Localised flaming was observed on the second
step some 12 minutes into the crib fire although this remained
localised until the test was completed. The steps immediately
over the crib sustained severe damage but this did not lead to
fire spread away from the crib location. At no stage did the
fire spread towards the half landing or the upper flight. Complete
combustion of the crib was reached after approximately 30 minutes
with no intervention necessary in contrast to the first trial.
For the crib fires, the higher temperatures
and lower oxygen levels recorded for Trial 1 illustrated a greater
rate of heat release and were indicative of the relative degree
to which the untreated stair was contributing to the fire. The
rapid drop in temperature shown in Trial 1 at just before 12
minutes was as a result of fire intervention using water spray
to suppress the fire. In contrast, despite an initially faster
development in the crib fire in Trial 2, the peak temperatures
recorded in the test compartment were nearly 50% of those recorded
in Trial 1 with a corresponding higher level of oxygen showing
a lower consumption of fuel (see
Figure 5).
Following the trial tests a number of recommendations
were made with respect to the main stair test on the TF2000 building.
These included
- Stairs would be treated using Dricon by Hickson Timber
Products
- Thermosetting adhesive (i.e. not thermoplastic) would
be used in the assembly of the stairs from the treated components.
A Urea Formaldehyde adhesive type was selected
- Stairs would be underdrawn with a single layer of 12.5mm
Gypsum Wallboard fixed using clout nails at a150mm centres
to the stringers of the stair only
- The test would use a double mattress identical to that
used in the stair trials 1 and 2 similarly located on the
ground floor of the building and tied back to the handrail
and spindles of the lower stair flight. In addition a single
crib, identical to that used in the stair trials and built
under the lower flight of stairs on the ground floor, would
be ignited simultaneously as would single strips of paraffin
soaked fibre board on the first five treads
- Following burn out of the fire load an inspection would
be carried out to assess the capability of the stairs as
a means of access and escape
The scenario for the main stair test on the
TF2000 building represented a significantly more severe test
than the original mattress fire in isolation. For this reason
it was decided to replicate the main TF2000 building test scenario
in a final trial.
The third trial test lasted for approximately
30 minutes with the plasterboard soffit protection to the stair
cracking and falling apart some 28 minutes into the test. However,
by this stage the fire load had been almost completely consumed.
No break out of fire through the treads or risers was observed
and the stairs remained usable following completion of the test.
The Main Test
In the fire condition, the ventilation conditions
within the full six-storey stair shaft of the TF2000 building
differed considerably from those present in the trial compartment
In terms of providing ventilation for the fire
and to ensure fire sustainability, the top window at 5th floor
(level 6) was left completely open for the test to provide exhaust
for fire gases. Inlet ventilation was provided by two openings
in the northern wall of the stair shaft that were sized so that,
together, they were equivalent in free area to the open widow
at 5th floor.
A large amount of instrumentation was installed
in the stair shaft, in the lobby areas and in adjacent rooms.
This included thermocouples (both type T and type K) to measure
air and element temperatures, aluminium billets to determine
heat flux, probes for oxygen and carbon monoxide concentrations,
smoke detectors, and load cells to measure burning rate. The
moisture content of the wood forming the timber crib was measured
at between 12 and 13%.
Fire development was very rapid following ignition.
Flames could be seen licking around the newel post and handrail
approximately 1 minute from ignition. The fibre strips soaked
in paraffin ignited some 3 minutes into the test and continued
to burn for approximately 12 minutes. At no stage was there any
spread of fire from this source. The mattress burned extremely
intensely and had been largely consumed by about 4.5 minutes
into the test.
Despite the areas of inlet and exhaust ventilation
being similar to those used in the trial an appreciably faster
flow of air was established in the test in the TF2000 stair shaft.
The velocity of smoke exhausting from the 5th floor (level 6)
stair shaft window was noted as being significant and was estimated
at approximately 5 metres per second. This through draught very
evidently dictated the path of flames at the seat of the fire.
The fire lasted for approximately 31 minutes.
At this stage the fire load had reduced to a few smouldering
embers. The Fire Brigade attended the test but did not have to
intervene to suppress the fire. Following combustion of the fire
load the integrity of the stair was confirmed by asking Fire
Brigade personnel in full equipment to use the stairs to access
the first and second floors.
The air temperatures at first and ground floor
level are shown in figure
6. Air temperatures remained below 300°C. The peak temperature
is due largely to the peak rate of heat release associated with
the mattress as no combustion of the handrail or spindles took
place. The location of the timber crib provided a worst case
in terms of the thermal exposure to the stairs although this
meant that the effect of the crib was very localised in terms
of the air temperature in the shaft.
Tenability Conditions During the Fire
Instrumentation was also provided to gather
data relevant to tenability conditions in the TF2000 building.
Smoke detector response in the test is summarised
in Table 1. As expected, fire was detected
first at the head of the stair shaft where it was expected that
smoke would rise and accumulate whilst exhausting from the 5th
floor window. The data shows earliest detection of the fire at
4 minutes and 21 seconds by the ionisation type smoke detector
at the head of the stair shaft. It is interesting to note that
ionisation and optical detector types that located in the same
vicinity gave very similar actuation times. The time taken for
carbon monoxide levels at the head of the stair shaft to reach
the actuation threshold of the domestic carbon monoxide detector
was somewhat longer. An analysis of instrument data indicated
that the carbon monoxide detector did not actuate until the oxygen
concentration significantly diminished. This coincided with the
fire burning at its maximum ferocity with the fire becoming ventilation
controlled and thus producing more products of less efficient
combustion including more carbon monoxide gas.
Figure
7 shows a record of carbon monoxide concentration monitored
close to the 5th floor lobby door on the lobby side at approximate
head height. What is noticeable is that the increase in detectable
carbon monoxide is concurrent with detector actuation in the
lobby at which time the vent panel was removed to simulate
automatic ventilation of the lobby. The peak carbon monoxide
concentration measured in the lobby was approximately.
The results of visibility measurements shown
in figure
8 indicated that the visibility diminished to about 10m and
the time of duration of the low visibility was coincident with
peak carbon monoxide levels.
Figure
9 shows levels of heat flux measured in the stair shaft.
At the underside of the 2nd floor half landing the peak heat
flux level reached 14 KW/m2 which is sufficient to cause the
pilot ignition of timber under sustained exposure. At 5th floor
level the peak heat flux was significantly lower with a peak
value slightly in excess of 5 KW/m2. This level of heat flux
is tolerable for about 12 seconds without suffering severe
sever pain.
The first automatic detection of the fire occurred at 4 minutes
and 21 seconds after ignition. Air temperatures monitored in the
stair shaft indicate that by 6 minutes conditions would have been
unpleasant enough to render the entire stair shaft untenable for
persons without protective clothing and breathing apparatus. Taking
into consideration human reaction time (longer if occupants asleep)
and the time needed to egress from flats, through the protected
lobbies and into the stair shaft, the time available between detection
and untenable conditions would not be regarded as sufficient time
to effect an escape from the building.
Hence the fire scenario used in the main stair test could be
considered as rendering the stair shaft untenable for means of
escape from the building during the fire. The timber structure
of the stair and shaft contributed insignificantly to the fire
event. Because of this it is appropriate to consider that similarly
untenable conditions would have prevailed were the test to have
been carried out in a masonry shaft with a non-combustible stair
construction.
Visibility and carbon monoxide data recorded in the 5th floor
lobby indicated that conditions in the protected lobbies of the
building would have remained tenable for occupants throughout
the fire event.
Post-fire Inspection
Following complete combustion of the fire load, the stairs were
visually inspected to ensure that they were still serviceable.
There was limited charring to the exposed stringers, the handrail
and the spindles. To demonstrate the ability of the stairs to
continue to meet the functional requirement for access and means
of escape, Fire Brigade personnel were asked to inspect the upper
floors using the stairs for entry. Fire fighters in full breathing
apparatus were able to access all levels without any difficulty – see
figure 10.
Conclusions
The test has demonstrated that the specific timber type and
treatment used for the experiment together provided an appropriate
level of fire performance to satisfy the functional fire safety
objectives for a stair in the residential building.
As a consequence of this research project, regulatory authorities
may wish to consider the use of an appropriately treated timber
stair as adequate in terms of meeting the functional requirements
of the UK Building Regulations, when used in a single stair medium-rise
building, on a case by case basis.
Key
Generic Features of the tested stair construction:
- Scissors type stair geometry
- Whitewood timber type
- Thermosetting type glue – Cascamite
- No stair coverings
- Pressure impregnated Hickson Timber Products
Ltd Dricon treatment process to give notional Class 1
reaction to fire performance
Future Work
In order to provide a link between the data generated from this
project and the standard tests that are carried out to establish
and classify the Reaction to Fire performance of materials, it
has been proposed that benchmark testing be carried out to national
and new European standards. Designers and enforcing authorities
will then be able to employ the research data to assess proposed
building designs incorporating single timber stairs where the
design of the stair differs from that which was evaluated in
the TF2000 fire experiments.