Overview
| Location: |
Madrid, Spain |
| Fire Event: |
12 February 2005
Fire started at the 21st Floor, spreading to all floors above
the 2nd Floor. Fire duration: 18 ~ 20 hours |
| Fire Damage: |
Extensive slab collapse above the 17th Floor. The building
was totally destroyed by the fire. |
| Construction Type: |
Reinforced concrete core with waffle slabs supported by
internal RC columns and steel beams, with perimeter steel
columns which were unprotected above the 17th Floor level
at the time of the fire. |
| Fire Resistance: |
Passive fire protection. No sprinklers. |
| Building Type: |
106 m (32 storeys). Commercial. |
The Building
The Windsor Tower or Torre Windsor (officially known as Edificio
Windsor) was a 32-storey concrete building with a reinforced
concrete central core. A typical floor was two-way spanning 280mm
deep waffle slab supported by the concrete core, internal RC
columns with additional 360mm deep steel I-beams and steel perimeter
columns. Originally, the perimeter columns and internal steel
beams were left unprotected in accordance with the Spanish building
code at the time of construction
The building featured two heavily reinforced concrete transfer
structures (technical floors) between the 2nd and 3rd Floors,
and between the 16th and 17th Floors respectively. The original
cladding system was fixed to the steel perimeter columns and
the floor slabs. The perimeter columns were supported by the
transfer structures at the 17th and 3rd Floor levels.
The building was subjected to a three year refurbishment programme
of works when the fire broke out. The major works included the
installations of:
- Fire protection to the perimeter steel columns using a boarding
system
- Fire protection to the internal steel beams using a spray protection
- A sprinkler system
- A new aluminium cladding system
The refurbishment was carried out floor-by-floor from the lower
floors upwards. By the time the fire broke out, the fire protection
for all steelwork below the 17th floor had been completed except
a proportion of the 9th and 15th floors. However, not all the
gaps between the cladding and the floor slabs had been sealed
with fireproof material (Dave 2005). Also fire stopping to voids
and fire doors to vertical shafts were not fully installed.
Fire Protection System
The Windsor Tower's original structural design complied
with the Spanish building codes in 1970s. At the time of the
construction,
the Spanish codes did not require fire protection to steelwork
and sprinkler fire protection for the building.
As a result, the original existing steelwork was left unprotected
and no sprinkler system was installed in the building. The gap
between the original cladding and floor slabs was not firestopped
as well. In fact, these weak links in the fire protection of
the building was being rectified in the refurbishment project
at the time of the fire.
Since the building adopted the "open plan" floor concept,
effectively, the fire compartmentation could only be floor-by-floor
(about
40 x 25m). However, the vertical compartmentation might not be
fully achieved due to the lack of firestop system in floor openings
and between the original cladding and the floor slabs.
The original fire protection system and the upgrading works
being carried out at the time of the fire are compared as follows
(NILIM 2005):
Main Fire Protection System |
At time of Construction
(1970s Spainish Codes) |
At Time of Fire
(Refurbishment in Process) |
Fire compartmentation |
× |
Under construction |
Fire stopping between
cladding & structure |
× |
Under construction |
Fire protection to steelwork |
× |
17th floor & above: Not yet commencement
(18th floor partly completed)
4th ~ 15th floor: Completed
(except 9 & 15th floors) |
Fire protection to concrete members |
× |
× |
Sprinkler system |
× |
Under construction |
Fire alarm system |
√ |
√ |
Dry riser system |
√ |
√ |
The Fire
The fire was believed to have been caused by a short-circuit
on the 21st floor. However, some facts under investigation point
that it could be induced by arsonists. The actual cause will
be difficult to be found due to the collapse of the break-out
floor.
It was reported that the fire started at 23:00 at the 21st Floor.
Within one hour, all floors above the 21st Floor were
on fire. In the following hours, the fire gradually spread downwards
to
the lower technical floor at the 3rd Floor. The total fire duration
was estimated to be 18 ~ 20 hours.
Based on the various sources of information, Table 1 shows the
estimated time frame for the fire development in the Windsor
Tower.
Table 1 Estimated time frame of fire development
(NILIM 2005) |
Time |
Fire Development |
Cross Section |
23:00 |
Fire started at the 21st Floor |
 |
23:05 ~ 23:20 |
After receiving a fire signal, the security guards went
to the 21st floor and attempting to fight the
fire before giving up |
23:21 |
Fire brigade was called |
23:25 |
Fire brigade arrived |
23:30 |
Fire brigade started to fight the fire (news report) |
00:00 |
All floors above the 21st floor were in fire
(news report) |
00:30 |
Fire brigade retreated and adopted a defensive position,
preventing fire spread to adjacent buildings |
02:00 |
Fire spread below the 17th floor |
02:15 |
Chunks of facade started falling off (news report) |
03:30 |
Fire spread below 16th floor, crossing over
the upper technical floor |
04:00 |
Floors at upper level collapsed (news report) |
05:30 |
Fire spread below the 12th floor (news report) |
08:30 |
Fire spread below the 4th floor |
13:30 |
Fire was under controlled |
17:00 |
Fire brigade declared the put out of the fire (news report) |
The Damage
The Windsor Tower was completely gutted by the fire on 12 February
2005. A large portion of the floor slabs above the 17th Floor
progressively collapsed during the fire when the unprotected
steel perimeter columns on the upper levels buckled and collapsed
(see Figure 1). It was believed that the massive transfer structure
at the 17th Floor level resisted further collapse of the building.
The whole building was beyond repair and had to be demolished.
The estimated property loss was €72m before the renovation.
Based on the footages of available media filming, Table 2 summarises
the estimated time frame for the structural collapses of the
Windsor Tower.
|
|
Figure 1 Collapse situation of the upper floors |
Table 2 Estimated time frame of collapses (NILIM
2005) |
Time |
Collapse Situation |
1:29 |
East face of the 21st floor collapsed |
1:37 |
South middle section of several floors above the 21st floor
gradually collapsed |
1:50 |
Parts of floor slab with curtain walls collapsed |
2:02 |
Parts of floor slab with curtain walls collapsed |
2:11 |
Parts of floor slab with curtain walls collapsed |
2:13 |
Floors above about 25th floor collapsed
Large collapse of middle section at about 20th floor |
2:17 |
Parts of floor slab with curtain walls collapsed |
2:47 |
Southwest corner of 1 ~ 2 floors below about 20th floor
collapsed |
2:51 |
Southeast corner of about 18th ~ 20th floors collapsed |
3:35 |
South middle section of about 17th ~ 20th floors collapsed
Fire broke through the Upper Technical Floor |
3:48 |
Fire flame spurted out below the Upper Technical Floor |
4:17 |
Debris on the Upper Technical Floor fell down |
Analysis
The main factors leading to the rapid fire growth and the fire
spread to almost all floors included:
-
the lack of effective fire fighting measures, such as automotive
sprinklers
-
the “open plan” floors with a floor area of 1000m2
-
the failure of vertical compartmentation measures, in the façade
system and the floor openings
It was believed that the multiple floor fire, along with the
simultaneous buckling of the unprotected steel perimeter columns
at several floors, triggered the collapse of the floor slabs
above the 17
th floor. The reduced damage below the 17
th floor
might provide a clue.
The fire protection on the existing steelworks below the 17th
floor had been completed at the time of fire except for the 9th
and 15th floors. When the fire spread below the 17th floor, those
protected perimeter columns survived, except for the unprotected
columns at the 9th and 15th floors which all buckled in the multiple
floor fire (see Figure 2). However, they did not cause any structural
collapse. Obviously, the applied loads supported by these buckled
columns had been redistributed to the remaining reinforced concrete
shear walls. Nevertheless, structural fire analysis should be
carried out before such a conclusion can be drawn.
 |
 |
| Figure 2 Buckling of unprotected steel perimeter
columns at the 9th floor (Photo: Colin Bailey) |
On the other hand, the reinforced concrete central core, columns,
waffle slabs and transfer structures performed very well in such
a severe fire. It is clear that the structural integrity and
redundancy of the remaining parts of the building provided the
overall stability of the building.
Sources of Information
- BBC News Online / World / Europe - UK Edition (13 Feb
2005)
-
Dave, P. (2005). “Madrid tower designer blames missing
fire protection for collapse”. New Civil Engineer, 2 June
2005.
-
[NILIM 2005] National Institute for Land and Infrastructure Management
(NILIM). (1 Jul 2005). “Report on the Windsor Building
Fire in Madrid, Spain”, Japan (in Japanese).