Overview
| Location: |
Los Angeles, USA |
| Date |
4 May 1988
|
| Fire Event |
Fire started at the 12th Floor and spread to four floors
above. Fire duration: 3 hours 40 minutes |
| Damage: |
Four fours were destroyed and one four was partially
damaged.
|
| Construction Type: |
Structural steel frame with lightweight
concrete slab on profiled steel deck.
|
| Fire Resistance: |
Sprayed fire protection to steelwork. Automatic sprinklers
system not yet commencement. |
| Building Type: |
262 m (62 storeys). Commercial.
|
The Building
The 262 m high, 62-story office tower was the tallest building
built in Los Angeles, USA, in 1973. The tower was known as the
UCB building until 1981, when United California Bank changed
its name to First Interstate Bank. The tower was renamed 707
Wilshire Tower in 1996 and became Aon Center in 2003.
The tower has a structural steel frame with lightweight concrete
slab on profiled steel deck. A typical floor measures 37.8 m
by 56.1 m, providing about 1,626 m2 of tenant area per floor
around a central service core which contains the lift and staircase
shafts. The external cladding system was made of glass and aluminium.
Fire Protection Systems
The fire protection system installed in the WTC towers at the
time of terrorist attack was summarised as follows:
Fire
Protection system
|
At
time of Construction
(1970s )
|
At Time
of Fire
(1988)
|
Fire compartmentation
|
Applied
to the central service core areas only. No fire-rated walls
used to separate the tenant places from each other.
|
Fire stopping between
cladding & structure
|
×
|
×
|
Fire protection to
steelwork
|
Spayed
fire protection materials
|
Sprinkler system
|
Not required by building
codes but had sprinkler protection in the basement, garage
and underground pedestrian tunnel
|
Automatic sprinkler
system was being installed in the building. 90% of the
work had been completed but not yet activated
|
Fire alarm system
|
√
|
√
|
Riser system
|
A single
zone combination standpipe system with four risers, one
in each stairway for each floor, supplied by two water
pumps
|
The Fire
The
source of fire was believed to be electrical in an open-plan
office area on the 12th floor. However, the precise source of
ignition was not determined.
The fire was believed to start before 22:25 at the 12th floor.
However, the ignoring of the alarms of smoke detectors delayed
the calling of fire brigade and fire fighting. The fire quickly
extended over the entire 12th floor except for the passenger
lift lobby in the central core and spread upwards until the 16th
floor through the gaps between the external cladding and the
floors.
The fire was finally put out by fire brigade at 02:19. The estimated
fire spreading rate was 45 minutes per floor and burned intensely
for approximately 90 minutes on each level. Two floors were heavily
involved in fire at any point during the fire.
It was found that smoke and heat travelled vertically above
the 12th floor through the floor openings, lift shafts and even
the pressurised stairwell. A minor fire occurred in a storeroom
on the 27th floor, ignited by fire products escaping from an
HVAC shaft that originated on the 12th floor. This fire self-extinguished
due to oxygen deficiency.
The estimated timeline for the fire development and fighting
is as follows:
Time
|
Damage
and Fire
|
22:22
|
Two fire pumps were shut down by sprinkler
contractor and the combination standpipe system was drained
down to the 58th floor level to facilitate connecting the
new sprinkler system to the standpipe at that level.
|
22:25
|
Glass failing was heard
and light smoke was seen at the ceiling level by the sprinkler
contractor. An alarm
on the 5th floor was pulled and after sounding for 2
seconds went dead.
|
|
|
A smoke detector on the 12th floor was
activated but reset by security personnel |
22:32
|
3 smoke detectors on the 12th floor
were activated and again reset by security personnel
|
22:34
|
4 smoke detectors on the 12th floor
were activated and reset
|
22:36
|
Multiple smoke detector alarms from the
12th to 30th floors activated. A maintenance
worker took the service elevator to the 12th floor
to investigate the
source of the alarms. The worker died when the lift door
opened onto a burning lobby on the 12th floor. |
22:37
|
Fire brigade was contacted by persons
outside the tower, reporting a fire on the upper floors
|
22:40
|
Fire brigade arrived and found that
the entire east side and there-fourths of the south side
of the 12th floor fully involved with fire
|
22:41
|
First report of the fire from inside
the building
|
22:49
|
Fire had spread upwards to the 13th and
14th floors
|
23:10
|
Fire brigade started to fight the fire |
01:30
|
The 15th floor was fully engulfed
in fire and the north end of the 16th floor started
to burn due to the fire through the space between the external
cladding
and the floor |
02:19
|
The fire was officially declared as put
out |
Damage
The total burnout of four and a half floors did not cause damage
to the main structural members due to a good application of spayed
fire protection on all steelwork. There was only minor damage
to one secondary beam and a small number of floor decks.
The non-structural damages included:
- Virtually all external cladding from the 12th to 16th floors
was destroyed and fell to the ground.
- The heat of the fire caused some aluminium alloy valves in
the occupant hose cabinets to fail, creating water leaks and
causing water damage on floors below the fire.
The property loss was estimated at over $200 million, excluding
the business interruption loss.
Analysis
The main factors leading to the rapid fire growth and the fire
spread to five floors included:
- the lack of effective fire fighting measures, such as automotive
sprinklers
- the delayed reporting of the fire
- the open-plan floors with a floor area of over 1600m2
- the failure of vertical compartmentation measures, in the
façade
system and the floor openings
The open-plan floors with large quantity of combustible office
contents without any internal fire barriers contributed to quick
fire growth within a fire floor. In addition, the gaps between
the external cladding and the floors were not firestopped and
the fire could easily spread to floors above. Without the effective
fire fighting on the 16
th floor by the fire brigade, the fire
could have spread to all floors above.
In fact, minor fire spreads also occurred through the floor
service openings for electricity and communications. This highlights
the importance of applying effective fire stopping system to
all floor and wall openings to ensure the effectiveness of fire
compartmentation.
It was also shown that if fire protection to structural members
is adequately designed and applied with quality control, fire
damage to fire exposed members will be minimised and structural
collapse can be prevented.
Sources of Information
- Los Angeles Fire Department / Historical Archive – Online
- Federal Emergency Management Agency. (1988). Interstate
Bank Building Fire – Los Angeles, California (May 4,
1988). United States Fire Administration Technical Report Series.